Windsor Road Construction Update April 20 2018
MAJOR ROADS
| LOCATION | DESCRIPTION |
APPROXIMATE COMPLETION DATE |
|
TECUMSEH ROAD EAST |
Tecumseh Road East from Hall Avenue to Turner Road will be reduced to one lane in each direction for water main and road construction. |
July 27, 2018 |
|
TECUMSEH ROAD EAST AT LITTLE RIVER BRIDGE |
Tecumseh Road East will be reduced to one lane in each direction from Yolanda Street to Penang Lane for the rehabilitation of the bridge over Little River Drain. All business access will be maintained however, left turn lanes will not be permitted through the construction zone. |
August 8, 2018 |
|
SEMINOLE ST. |
Seminole St. from George Avenue to Central Avenue will be closed for water main and road reconstruction.
Start Date: April 23, 2018 |
July 13, 2018 |
MINOR ROADS
| LOCATION |
DESCRIPTION |
APPROXIMATE COMPLETION DATE |
|
MOY AVE. |
Moy Avenue from Wyandotte Street East to Riverside Drive will be restricted to local traffic for water main & road rehabilitation |
April 30, 2018 |
|
CONNAUGHT AVE. |
Connaught Avenue from Prince Road to Felix Avenue will be restricted to local traffic for road rehabilitation |
May 31, 2018 |
WINDSOR UTILITIES COMMISSION (WUC) PROJECTS
| LOCATION | DESCRIPTION |
APPROXIMATE COMPLETION DATE |
|
DOUGALL AVE. |
Dougall Avenue between Ellis Street and Tecumseh Road will be closed (local traffic only) for water main construction. |
May 11, 2018 |
|
GIRARDOT ST. |
Girardot Street from Prince Road To Brock Street will be closed (local traffic only) for water main construction. |
June 29, 2018 |
|
BROCK ST. |
Brock Street between Mulford to Baby Street will be closed (local traffic only) for water main construction. |
June 29, 2018 |
|
FELIX AVENUE |
Felix Avenue between Mill Street and Edison Street will be closed (local traffic only) for water main construction. |
2018-04-13 |